Saturday, 18 May 2013

Grouted

Block and beam floor has been grouted and you can see the shape of the rooms starting to appear.


Wednesday, 8 May 2013

Footings complete

Footings complete, drains installed ready for the block and beam floor.

Thursday, 2 May 2013

Footings day four

Getting ready to install the drain pipes.