Monday, 29 April 2013

Footings day one

The foot print of the Riseley Eco Cottage is taking shape as the block work progresses.


Friday, 26 April 2013

Blocks

The blocks are laid out ready for the bricklayers on Monday to build the walls up from the foundations to the damp proof course.



Thursday, 18 April 2013

Big Day Today -Concrete in Foundations

Big day today as we now have concrete in all the foundations and we are getting up out of the ground.




Wednesday, 17 April 2013

Reinforcing Mesh In The Trenches


The reinforcing mesh is in the trenches ready for the concrete




Tuesday, 16 April 2013

Steel Reinforcing Mesh

Steel reinforcing mesh ready to go into the foundations of the Riseley Eco Cottage


Monday, 15 April 2013

Site Hut


Every site needs a site hut for the construction team. The Riseley Eco Cottage has a replica Shepherd's Hut

Thursday, 11 April 2013

Construction has started

We are pleased to be able to tell you that construction of the Riseley Eco Cottage has started. We are currently lowering the ground level so that cottage has a low profile and sits comfortably with the adjoining houses.

The the next step will be putting in the foundations and this will involve more concrete and steel than we would really like for an eco cottage. We also are taking care to construct our foundations in such a way as to avoid damage to a eucalyptus tree in the adjacent garden.