Monday, 29 April 2013

Footings day one

The foot print of the Riseley Eco Cottage is taking shape as the block work progresses.


Friday, 26 April 2013

Blocks

The blocks are laid out ready for the bricklayers on Monday to build the walls up from the foundations to the damp proof course.



Thursday, 18 April 2013

Big Day Today -Concrete in Foundations

Big day today as we now have concrete in all the foundations and we are getting up out of the ground.




Wednesday, 17 April 2013

Reinforcing Mesh In The Trenches


The reinforcing mesh is in the trenches ready for the concrete




Tuesday, 16 April 2013

Steel Reinforcing Mesh

Steel reinforcing mesh ready to go into the foundations of the Riseley Eco Cottage


Monday, 15 April 2013

Site Hut


Every site needs a site hut for the construction team. The Riseley Eco Cottage has a replica Shepherd's Hut